Max Rosenn U.S. Courthouse
Project
Situated inside a historical building in a busy city, this office area was renovated to accommodate modern, state-of-the-art technology, while maintaining its historical integrity. A primary focus of the job was to preserve and highlight the original ceilings. An impressive, high end conference room was also added.
Challenges
- Since the renovation work had to be conducted in a fully operational space, L.R. Costanzo was tasked with minimizing the exposure of the construction and subsequent noise.
- Maintaining the integrity and matching the fabric/color of the historical ceiling.
- Safety for the craftsmen during the removal and reinstallation of the historic metal ceiling.
Solutions
- Constantly communicated and coordinated with the owner and subcontractors regarding the work schedule; installed temporary partitions with used noise-reduction materials.
- Carefully documented ceiling pieces using photography in order to reposition after restoration; worked closely with vendors/suppliers of historic-grade materials in order to match missing pieces.
- Conducted safety meetings, utilized a safe plan of action and enforced strict safety practices.
Construction Details
L.R. Costanzo experts also:
- Upgraded mechanical and electrical systems for the increased building load.
- Removed, reinstalled and replicated historical metal ceiling.
- Made extensive floor repairs and leveling.
- Removed and replaced existing steel windows.
- Installed an automatic projection screen in the modern conference room.