Pharmaceutical Client | Building Renovation
PROJECT
This building renovation to existing laboratories included major interior, exterior and structural demolition work prior to renovation.
CHALLENGES
- Building operations maintained during construction
- Fast-track project required heavy structural demolition and three-month completion
SOLUTIONS
- Isolation barriers and engineering controls designed and constructed by qualified craftsmen
- Double-shift operation
CONSTRUCTION DETAILS
L.R. Costanzo experts procured and installed:
- Laboratory equipment, casework and fume hoods
- Class 100,000 laboratories
- Executive conference room
- Administrative offices