Pharmaceutical Client | Vaccine Manufacturing Facility


Vaccine Manufacturing Facility
Eastern PA
Owner
Pharmaceutical Client
Eastern, PA

Design Professional
Sear-Brown Vestal, NY
PROJECT
This new manufacturing facility was constructed of fifty-two modular units imported from Europe. L.R. Costanzo’s work scope for the project was to provide additional space in the facility by constructing a second floor addition to accommodate a conference room, office space, and break area. The second portion of the project was to provide a uniform façade for the entire structure. Also constructed were a collection tank, process piping and controls to automate the facility’s phenol supply and removal throughout the production area.
CHALLENGES
- Start up and commissioning of production spaces underway during construction
- Limited design documents
- Limited budget
- Limited staging & site access – had to keep road open
SOLUTIONS
- Tight work schedule coordination with owner
- Collaborative design effort with facilities architect
- Value engineering
- Careful coordination and planning. Scheduled steel erection on weekends to keep road free during heavy traffic times
CONSTRUCTION DETAILS
L.R. Costanzo experts coordinated, scheduled and constructed:
- New glass entrance with canopy roof
- Brick, metal panels, windows and dryvit for the building’s new façade
- HVAC systems in the addition
- Installed loading dock equipment and overhead doors