Pharmaceutical Client | Waste Water Treatment Plant

Waste Water Treatment Plant
Upgrade

Eastern PA

Owner

Pharmaceutical Client
Eastern, PA

Design Professional

BCM Engineers
Plymouth Meeting, PA

m

PROJECT

The project consisted of a new addition to the company’s existing Waste Water Treatment Plant, along with a total upgrade of the existing facility. Installation of specific mechanical piping was crucial to this project’s success. During this project, the adjacent facility was on-line and in full production. Necessary precautions were taken to ensure that the operating facility would not be impacted.

CHALLENGES

  • Plant had to remain “on-line”
  • Plant operators needed to manually operate plant
  • Coordination and planning to tie new systems into existing systems
  • Delivery and installation of precise and complex mechanical materials
  • Safety was the priority due to heavy material installation which would easily cause injury

SOLUTIONS

  • Installed by-pass pumps and temporary tanks to redirect flow
  • Installed technology upgrades in a phased approach to automate system
  • Daily schedules detailed completion of designated systems
  • Constant communication with equipment suppliers and subcontractors
  • Frequent safety meetings to discuss potential hazards and solutions

CONSTRUCTION DETAILS

L.R. Costanzo experts also procured and installed:

  • Complex mechanical systems
  • Tie-ins of new systems into existing systems